PRE-COMMISSION CLEANING OF A PRE-FLUSHED SYSTEM
- Ensure that all low points and dead legs contain valved
drain connections as large as is practically possible for
full bore flushing.
- Fill system with mains water, vent re-circulate and check
for leaks.
- Areas of low flow or restrictions (e.g. Staefer valves etc.)
should be isolated or bypassed.
- Add GO-THERM CL28 via dosing
pot (already installed) until product reserve of 1.0 - 2.0%
minimum is achieved.
- Allow system to re-circulate with heat on (if possible)
for a minimum period of 24 hours. Maintain a series of continuous
checks to ensure that the treatment levels are within parameters
(as in item 4 above) and no accumulations of debris is taking
place within areas of flow. Take regular checks of iron levels,
pH and electrical conductivity and tabulate over the cleaning
period. When deposit plateau achieved with an excess of cleaning
agent, proceed to stage (6).
- System to be dynamically flushed (i.e. drain from each outlet
point with circulating pumps running, whilst maintaining constant
supply of make up water). It is important to ensure that flushing
velocities are maintained as near to 2.0 m/sec within all
areas of the system. It may be necessary to isolate parts
of the system temporarily to achieve these velocities or install
auxiliary pumps.
- To monitor any sediment remaining within the system following
the clean and to ensure the customer that steps have been
taken to minimise any problems the following action will be
taken:
- On all systems where FCU's are installed with flexible
bypass couplings the following action will be taken:
- A. On each floor layout, the last two units will be
isolated on the LTHW and chilled water circuits.
This action would be taken wherever access is possible and
in situations where the distributions pipe-work is not hard
piped to the FCU's. Where the units are installed with hard
piping then any appropriate action such as flushing via drain
off cocks should be applied. In cases where the above actions
reveal problems the immediate notification to Business Manager
or Chemical Cleaning co-ordinator must occur.
- Top up system and return to service and dose with the relevant
water treatment corrosion inhibitor, i.e. GO-THERM
CW25L.
- Check and clean all strainers and recheck all drain points
for possible accumulations of light debris not removed by flushing
process.
ON SITE REQUIREMENTS
In order to carry out the work Gower Environmental
Services shall require the contractor to provide the following:
- All systems to be flushed and filled with fresh clean water
at the commencement of work. We would emphasise the importance
in removing excess jointing compound, e.g. Bosswhite and hemp
as this type of deposit cannot be chemically removed.
- 220/240 or 110 volt single phase electrical supply within
Plant Rooms and near the incoming mains terminal point.
- Adequate supply of fresh towns main water and connection
to completely fill all systems simultaneously in 4 hours.
To meet this requirement we would suggest that a 2 ins BSP
minimum supply be available. The amount of water required
during the whole process is approximately four time the systems
capacities.
- Point for disposal of effluent to enable all systems to
be drained simultaneously with all drain valves fully opened.
- All systems circulating pumps to be operational during the
complete process. The success of our pre commission cleaning
will depend on obtaining a minimum flow rate of 0.5 mt per
second throughout every circuit.
- Minimum 1.5 ins BSP connections on flow and return pipe-work
at lowest point in the system for injection of chemicals and
draining down.
- At all other low areas which cannot be emptied from the main
drains item to have ¾" BSP drains or largest possible in pipe-work
under ¾" diameter.
- Any item that will restrict the flushing procedures, must
be bypassed or removed and terminal points cross connected.
Examples of some items that cause problems are: fine in line
filters, orifice plates and some types of control valves,
fan coil units.
- All dead legs terminal points to be cross connected between
flow and return, in order that adequate circulation can be maintained
during and after the cleaning process. Ideally the cross connections
should be the same diameter as the pipe-work in order to facilitate
unrestricted flow.
- Adequate vents in each system to enable air to be purged
during filling, without restricting the specified time to
completely fill the system main vents should be a min bore
of 1.5 ins.
- An Engineer familiar with the system to advise our operators
on the operation of valves, pumps etc., to ensure the whole
system is circulated during the process.
- Access to the whole system during the complete process.
- The system must be completely flushed, pressure tested and
be sound with no leaks prior to arrival on site.
- Drawings of each system to be available to Gower Environmental
Services personnel upon or prior to our arrival on site.
- All drains to be used for draining down must be sound and
capable of taking the required flow rate.
- Where the system contains any unusual materials, equipment
or other fittings or components Gower Environmental Services
must be notified of their presence
|
Water Treatment
Pre-commission cleaning
and chlorination
Own label chemicals
Contact us
Quality
|